Completed Projects

MUNICIPAL PROJECTS INFORMATION CENTER

Completed Projects:

LEES AVE REPAVING PROJECT

Location: Lees Avenue from Ventnor Avenue to Belmont Avenue
Anticipated Project Start: September 2023
Work will include: resurfacing, full depth reconstruction, concrete curbing, ADA compliant ramps and sidewalk and driveway improvements on Lees Avenue from Ventnor Avenue to Merrick Avenue. 

WATER MAIN REPLACEMENT PROJECT
Location: Conger Ave from Tatem to King, N Vineyard Blvd from Highland to Garfield
Project Start Date: January 17, 2022
Test pit excavation begins December 2021
Anticipated Project Length: 3 months

Work will include:

  • Installation of new water main in accordance with current New Jersey Department of Environmental Protection and Water Accountability Act standards
  • Water services replaced from main to curb shutoff
  • New hydrants and control valves
  • Roadway trench restored
  • Driveway, sidewalk, curb, and curb ramp replacements in select areas

Due to technology issue the Jan. 13 Neighborhood Meeting was canceled. We distributed a notice to residents in the impacted area to provide project information that would have been presented at the meeting. View a copy of the notice here.  Additional notices will be provided to the affected area via doorhangers as construction progresses. With any project questions, contact Borough Engineer Tim Staszewski  at 856-795-9595 x1094 or  timothy.staszewski@rve.com  or Borough Administrator Cassandra Duffey at 856-854-0720 x125 or cduffey@collingswood.com.


GRANT AVE REPAVING PROJECT - PART III
White Horse Pike (Rt 30) to W. Browning Rd
New Anticipated Start Date: Spring 2022
Anticipated Project Length: 4-6 weeks

Work will include:

  • Select curb, sidewalk, and driveway aprons
  • New inlet structures, grates, and curb heads
  • Removal of the existing roadway surface
  • Recontouring of select areas of roadway gutter for improved drainage
  • Paving of the roadway with new blacktop
  • New traffic markings and signage

See Oct 19 neighborhood meeting here.

With questions contact:
Tim Staszewski - Borough Engineer
856-795-9595 x1094 timothy.staszewski@rve.com

Cassandra Duffey - Borough Administrator
856-854-0720 x125cduffey@collingswood.com

GRANT AVENUE REPAVING PROJECT - PART I
Champion Ave to White Horse Pike (Rt 30)
Project Start Date: October 7, 2020
Anticipated Project Length: 4-6 weeks

Work will include:

  • Select tree removal
  • Trimming of dead tree branches.
  • Select curb, sidewalk, and driveway aprons
  • New ADA curb ramps
  • New inlet structures, grates, and curb heads
  • Select sump pump connection to the storm main
  • Removal of the existing roadway surface
  • Paving of the roadway with new blacktop
  • Planting of new street trees
  • Concrete crew will start on the even side of the street, near WHP, work towards Champion, then flip to the odd side
  • Access to properties will generally be maintained for the duration of the project

Grant Avenue repaving plans can be viewed here.


GRANT AVENUE REPAVING PROJECT - PART II
White Horse Pike (Rt 30) to W. Browning Rd
Project Start Date: Fall 2021
Anticipated Project Length: 4-6 weeks

Work will include:

  • Select tree removal
  • Trimming of dead tree branches
  • Select curb, sidewalk, and driveway aprons
  • New ADA curb ramps
  • New inlet structures, grates, and curb heads
  • Select sump pump connection to the storm main
  • Removal of the existing roadway surface
  • Paving of the roadway with new blacktop
  • Planting of new street trees

A neighborhood meeting was held to discuss project scope and answer resident questions. Watch the recording:  Grant Ave Re-Paving Neighborhood Meeting 5.26.21


SAFE ROUTES TO SCHOOL AND TRAFFIC CALMING
Project Start Date: January 18, 2021
Anticipated Project Duration: 4 months

Project Locations:
Phase 1 - Maple Ave at Washington, Frazier, Lawnside, E. Stiles, and E. Homestead
Phase 1- Lincoln Ave at Cedar and Washington
Phase 1 - Atlantic Ave at Lees, Edison, Coolidge, Dill, Curtis, Cooper, and W. Homestead
Phase 2 - Dill Ave from Stokes Ave to Atlantic Ave
Phase 2 - Stokes Ave at Lees Ave and Lees Lane
Phase 2 - Lees Lane from Stokes Ave to Linwood Ave
Phase 3 - Haddon Ave at Homestead Ave

Work will include:

  • New ADA Curb Ramps
  • New Crosswalks
  • Signage
  • Intersection Bump Outs for traffic calming and pedestrian safety at Haddon/Homestead
  • New Drainage pipe and inlets
  • Decorative brick pavers
  • Select Concrete Roadway Slab Replacement

Meetings and recordings:

The Safe Routes to School (SRTS) grant is a federal grant that promotes walking and bicycling to school through infrastructure improvements. Collingswood was awarded roughly $900,000 to make these improvements. Read more here.


CURRENT PROJECTS:
CLICK HERE FOR ACTIVE PROJECTS