MUNICIPAL PROJECTS INFORMATION CENTER
Completed Projects:
LEES AVE REPAVING PROJECT
Location: Lees Avenue from Ventnor Avenue to Belmont Avenue
Anticipated Project Start: September 2023
Work will include: resurfacing, full depth reconstruction, concrete curbing, ADA compliant ramps and sidewalk and driveway improvements on Lees Avenue from Ventnor Avenue to Merrick Avenue.
WATER MAIN REPLACEMENT PROJECT
Location: Conger Ave from Tatem to King, N Vineyard Blvd from Highland to Garfield
Project Start Date: January 17, 2022
Test pit excavation begins December 2021
Anticipated Project Length: 3 months
Work will include:
- Installation of new water main in accordance with current New Jersey Department of Environmental Protection and Water Accountability Act standards
- Water services replaced from main to curb shutoff
- New hydrants and control valves
- Roadway trench restored
- Driveway, sidewalk, curb, and curb ramp replacements in select areas
Due to technology issue the Jan. 13 Neighborhood Meeting was canceled. We distributed a notice to residents in the impacted area to provide project information that would have been presented at the meeting. View a copy of the notice here. Additional notices will be provided to the affected area via doorhangers as construction progresses. With any project questions, contact Borough Engineer Tim Staszewski at 856-795-9595 x1094 or timothy.staszewski@rve.com or Borough Administrator Cassandra Duffey at 856-854-0720 x125 or cduffey@collingswood.com.
GRANT AVE REPAVING PROJECT - PART III
White Horse Pike (Rt 30) to W. Browning Rd
New Anticipated Start Date: Spring 2022
Anticipated Project Length: 4-6 weeks
Work will include:
- Select curb, sidewalk, and driveway aprons
- New inlet structures, grates, and curb heads
- Removal of the existing roadway surface
- Recontouring of select areas of roadway gutter for improved drainage
- Paving of the roadway with new blacktop
- New traffic markings and signage
See Oct 19 neighborhood meeting here.
With questions contact:
Tim Staszewski - Borough Engineer
856-795-9595 x1094 | timothy.staszewski@rve.com
Cassandra Duffey - Borough Administrator
856-854-0720 x125 | cduffey@collingswood.com
GRANT AVENUE REPAVING PROJECT - PART I
Champion Ave to White Horse Pike (Rt 30)
Project Start Date: October 7, 2020
Anticipated Project Length: 4-6 weeks
Work will include:
- Select tree removal
- Trimming of dead tree branches.
- Select curb, sidewalk, and driveway aprons
- New ADA curb ramps
- New inlet structures, grates, and curb heads
- Select sump pump connection to the storm main
- Removal of the existing roadway surface
- Paving of the roadway with new blacktop
- Planting of new street trees
- Concrete crew will start on the even side of the street, near WHP, work towards Champion, then flip to the odd side
- Access to properties will generally be maintained for the duration of the project
Grant Avenue repaving plans can be viewed here.
GRANT AVENUE REPAVING PROJECT - PART II
White Horse Pike (Rt 30) to W. Browning Rd
Project Start Date: Fall 2021
Anticipated Project Length: 4-6 weeks
Work will include:
- Select tree removal
- Trimming of dead tree branches
- Select curb, sidewalk, and driveway aprons
- New ADA curb ramps
- New inlet structures, grates, and curb heads
- Select sump pump connection to the storm main
- Removal of the existing roadway surface
- Paving of the roadway with new blacktop
- Planting of new street trees
A neighborhood meeting was held to discuss project scope and answer resident questions. Watch the recording: Grant Ave Re-Paving Neighborhood Meeting 5.26.21
SAFE ROUTES TO SCHOOL AND TRAFFIC CALMING
Project Start Date: January 18, 2021
Anticipated Project Duration: 4 months
Project Locations:
Phase 1 - Maple Ave at Washington, Frazier, Lawnside, E. Stiles, and E. Homestead
Phase 1- Lincoln Ave at Cedar and Washington
Phase 1 - Atlantic Ave at Lees, Edison, Coolidge, Dill, Curtis, Cooper, and W. Homestead
Phase 2 - Dill Ave from Stokes Ave to Atlantic Ave
Phase 2 - Stokes Ave at Lees Ave and Lees Lane
Phase 2 - Lees Lane from Stokes Ave to Linwood Ave
Phase 3 - Haddon Ave at Homestead Ave
Work will include:
- New ADA Curb Ramps
- New Crosswalks
- Signage
- Intersection Bump Outs for traffic calming and pedestrian safety at Haddon/Homestead
- New Drainage pipe and inlets
- Decorative brick pavers
- Select Concrete Roadway Slab Replacement
Meetings and recordings:
- Phase 1 neighborhood meeting recording (Jan 20)
- Phase 2 neighborhood meeting (Feb 25)
- Phase 3 neighborhood meeting (April 20) - no attendance/ no meeting recording
The Safe Routes to School (SRTS) grant is a federal grant that promotes walking and bicycling to school through infrastructure improvements. Collingswood was awarded roughly $900,000 to make these improvements. Read more here.
CURRENT PROJECTS:
CLICK HERE FOR ACTIVE PROJECTS